Subject:
|
Technic model construction time
|
Newsgroups:
|
lugnet.technic
|
Date:
|
Tue, 24 Jul 2001 03:44:49 GMT
|
Viewed:
|
952 times
|
| |
| |
How long does does it take all of you to build a typical Technic custom
creation/MOC? (the larger ones in general, such as the type that are usually
displayed on Lugnet) For me it is usually between two and four months,
working on the model for three of four hours each day. (although my current
project will probably pass the 4-month limit...LOL) Several times I have had
to scrap ideas for a model due to some problem or another (sometimes even
start from scratch) or work out an alternate way of completing a task, which
adds to the overall time required.
-Gaurav Thakur, raving madman
Can be reached at cp5670@supermail.com
http://cp5670.250x.com/TC/
|
|
Message has 2 Replies: | | Re: Technic model construction time
|
| (...) This is a good question. I'm also curious as to the time it takes other builders to make such MOCs. From my experience on my big crawler crane, I've estimated that it took me 200 to 250 hours straight building time. However, that was spread (...) (23 years ago, 24-Jul-01, to lugnet.technic)
| | | Re: Technic model construction time
|
| A good question. The planning stages, just using paper & pencil, graphic calc from time to time, takes about 2 to 8 weeks. No really fancy plans on paper or screen, just number values and sketches. The prototype stage can take 1 to 12 hours straight (...) (23 years ago, 25-Jul-01, to lugnet.technic)
|